Capital Improvement Projects (CIP)

Construction Markups Updated September 28, 2020

Construction Markups Updated September 14, 2020

Construction Markups Updated September 8, 2020

Construction Markups Updated August 31, 2020

AAMD Distribution System Improvement Project Final Engineering Drawings 8-17-2020

Master Schedule Updated 8-6-2020

Pay App No. 1 (3rd revision) 7-24-2020

Change Order #1 7-23-2020

AAMD Distribution System Improvement Project Final Engineering Drawings

MASTER SCHEDULE 6-19-2020

Project Layout

UPCOMING CONSTRUCTION SCHEDULE:

9/28/2020 Construction Update Native Sun Distribution Project Schedule: This Week the crews will be finishing raw water line, tie-ins to existing system (top of Jenwood 9/28, and Gerka/Lady Lane Intersection 9/30.) Services: Services along Banner, Kenwood, Deer Ridge, Denwood, Jenwood, Lady Lane, Gerka. Testing: Testing for Denwood, Jenwood, Deer Ridge, Gerka, Lady Lane, and raw waterlines.

9/14/2020 Construction Update Native Sun Distribution Project Schedule: This week, crews will be finishing connections to the existing system. Adding more appurtenances to the new pipe, and working mainline along Banner. They will also be testing the new system (flushing, chlorine, and pressure). Crews will also be completing site work at both control buildings, and pouring concrete pads.

9/8/2020 Contruction Update Native Sun Distribution Project: The crews will be finishing connections to the existing system, adding more appurtenances to the new pipe, and working mainline along Banner, hopefully completing that this week. They will also be testing the new system (flushing, chlorine, and pressure). 

8/31/2020 Construction Update: Native Sun: Distribution Project: This Week: The contractor is doing tie in work. The contractor will work along Denwood, Deer Ridge and Banner. We should be completing Denwood and closing up the intersection at Deer Ridge Monday or Tuesday.

Glacier: Treatment Project: This Week: Pouring concrete at control building A and B.

8/26/2020 Construction Update: Deer Ridge will be closed at Silbani tomorrow and Denwood will be open but also under construction. Thank you for your patience and understanding during this time.

8/17/2020 Update: This week, the contractor will be completing the tie work along Deer Ridge to Jenwood. If the contractor gets far enough along, he will begin work down Banner.

7/23/2020 Update: Today the crews will be working along Gerka and at the easement between the Upper and Lower Gerkas.

7/20/2020 Update: This week, the Contractor will be working along Tidi and Banner. Contractor will work along Gerka if he gets to the Donzi and Banner Intersection. Contractor will also be working between Well #6 and Well #7 once the locates are completed and possibly the line between Upper and Lower Gerka.

7/13/2020 Update: The Contractor will be working along Donzi and expects to get to Tidi by the end of the week.

7/7/2020 Update: Today and tomorrow we will be working near our well fields at our Main Control Building A on Silbani Lane near Donzi Circle.  Later this week, we will be working on Donzi Circle from the tank to Banner Trail.

UPDATE: Construction on Donzi from the tank to Sildona is now set to begin on Tuesday, July 7, 2020. Please check back for updates as they are available.

*Main Line work, in the street construction is scheduled for the following areas:

7/1/2020 – 7/6/2020 Donzi from the tank to Sildona.

7/7/2020 -7/13/2020 Tidi from Banner to Gerka, then all of Gerka

7/14/2020 – 7/16/2020 Tidi from Donzi to Banner, Banner from Golden

7/17/2020 – 7/24/2020 Banner from Golden, Jenwood and Denwood

7/27/2020 – 7/30/2020 Kenwood, intersection of Dilbani and Deer Ridge, and Deer Ridge to County Road 42

8/3/2020 – 8/6/2020 Silbani between Donzi and Deer Ridge

*Residential taps—connecting houses to main line construction is scheduled for the following areas:

8/7/2020 – 8/13/2020 23 homes on Donzi

8/14/2020 – 8/17/2020 11 homes Tidi from Banner to Gerka, then all of Gerka

8/18/2020 – 8/20/2020 13 homes Tidi from Donzi to Banner, Banner from Golden

8/21/2020 – 8/27/2020 24 homes Banner from Golden, Jenwood and Denwood

8/28/2020 – 9/1/2020 15 homes  Kenwood, intersection of Dilbani and Deer Ridge, and Deer Ridge to County Road 42

9/2/2020 – 9/3/2020 7 homes Silbani between Donzi and Deer Ridge

*ARV Vaults:

9/4/2020 – 9/9/2020 Air Release Valve Installation—Road work throughout the district

*Road Regrading:

9/10/2020 – 9/28/2020 Road Regrading throughout the district

Please find important documents and information on the Arabian Acres Metropolitan District capital improvement project below.

Frequently Asked Questions on Proposed Capital Project

SRF Loan Application 02/15/2020

AAMD Capital Financing Worksheet

AAMD Capital Project Budget

The Arabian Acres Metropolitan District submitted the attached Construction Application for improvements to its potable water treatment system to the Colorado Department of Public Health and Environment. The full Construction Application Report can be found here: Arabian Acres Construction Application Report (1-16-2020) Due to the size of the document, we have broken it up into parts for easy access:

AAMD Capital Project Construction Application Submittal Part 1

AAMD Capital Project Construction Application Submittal Part 2

AAMD Capital Project Construction Application Submittal Part 3

AAMD Capital Project Construction Application Submittal Part 4 Specs

AAMD Capital Project Construction Application Submittal Part 5 Specs 2

AAMD Capital Project Construction Application Submittal Part 6 Specs 3

AAMD Capital Project Construction Application Submittal Part 7 Specs 4

The Water Meter Project was completed on October 10, 2019.