Capital Improvement Projects (CIP)

Master Schedule Updated 8-6-2020

Pay App No. 1 (3rd revision) 7-24-2020

Change Order #1 7-23-2020

AAMD Distribution System Improvement Project Final Engineering Drawings

MASTER SCHEDULE 6-19-2020

Project Layout

UPCOMING CONSTRUCTION SCHEDULE:

7/23/2020 Update: Today the crews will be working along Gerka and at the easement between the Upper and Lower Gerkas.

7/20/2020 Update: This week, the Contractor will be working along Tidi and Banner. Contractor will work along Gerka if he gets to the Donzi and Banner Intersection. Contractor will also be working between Well #6 and Well #7 once the locates are completed and possibly the line between Upper and Lower Gerka.

7/13/2020 Update: The Contractor will be working along Donzi and expects to get to Tidi by the end of the week.

7/7/2020 Update: Today and tomorrow we will be working near our well fields at our Main Control Building A on Silbani Lane near Donzi Circle.  Later this week, we will be working on Donzi Circle from the tank to Banner Trail.

UPDATE: Construction on Donzi from the tank to Sildona is now set to begin on Tuesday, July 7, 2020. Please check back for updates as they are available.

*Main Line work, in the street construction is scheduled for the following areas:

7/1/2020 – 7/6/2020 Donzi from the tank to Sildona.

7/7/2020 -7/13/2020 Tidi from Banner to Gerka, then all of Gerka

7/14/2020 – 7/16/2020 Tidi from Donzi to Banner, Banner from Golden

7/17/2020 – 7/24/2020 Banner from Golden, Jenwood and Denwood

7/27/2020 – 7/30/2020 Kenwood, intersection of Dilbani and Deer Ridge, and Deer Ridge to County Road 42

8/3/2020 – 8/6/2020 Silbani between Donzi and Deer Ridge

*Residential taps—connecting houses to main line construction is scheduled for the following areas:

8/7/2020 – 8/13/2020 23 homes on Donzi

8/14/2020 – 8/17/2020 11 homes Tidi from Banner to Gerka, then all of Gerka

8/18/2020 – 8/20/2020 13 homes Tidi from Donzi to Banner, Banner from Golden

8/21/2020 – 8/27/2020 24 homes Banner from Golden, Jenwood and Denwood

8/28/2020 – 9/1/2020 15 homes  Kenwood, intersection of Dilbani and Deer Ridge, and Deer Ridge to County Road 42

9/2/2020 – 9/3/2020 7 homes Silbani between Donzi and Deer Ridge

*ARV Vaults:

9/4/2020 – 9/9/2020 Air Release Valve Installation—Road work throughout the district

*Road Regrading:

9/10/2020 – 9/28/2020 Road Regrading throughout the district

Please find important documents and information on the Arabian Acres Metropolitan District capital improvement project below.

Frequently Asked Questions on Proposed Capital Project

SRF Loan Application 02/15/2020

AAMD Capital Financing Worksheet

AAMD Capital Project Budget

The Arabian Acres Metropolitan District submitted the attached Construction Application for improvements to its potable water treatment system to the Colorado Department of Public Health and Environment. The full Construction Application Report can be found here: Arabian Acres Construction Application Report (1-16-2020) Due to the size of the document, we have broken it up into parts for easy access:

AAMD Capital Project Construction Application Submittal Part 1

AAMD Capital Project Construction Application Submittal Part 2

AAMD Capital Project Construction Application Submittal Part 3

AAMD Capital Project Construction Application Submittal Part 4 Specs

AAMD Capital Project Construction Application Submittal Part 5 Specs 2

AAMD Capital Project Construction Application Submittal Part 6 Specs 3

AAMD Capital Project Construction Application Submittal Part 7 Specs 4

The Water Meter Project was completed on October 10, 2019.